1.Objective:
This document is created to provide enough information to operation team for or carrying out the Boiler cold start up activity safely and smoothly.
2.Equipment details:
Make: XXX
Working pressure/Temperature: 110
kg/cm2/545 deg C
Capacity: 115 TPH
Shift In charge, Control room engineers and Boiler
operators
Safety shoes,
safety helmet, Face shield, Safety goggles, Boiler apron, hand gloves, ear
plugs
Fire wood, charcoal, diesel and
pocking rods, walkie- talkies, Bagasse, coal, tractor dozers, JCB etc
Shift In charge, Boiler Control room engineer, Boiler 1st
class and 2nd class operator, Ash handling operator, Bunker/Silo
operator, Fuel yard operators, Mechanical technicians unskilled labours for
Boiler and supporting E&I engineer/Technician.
7.Potential Hazards Identified:
Back fire,
flue gas leakage, steam & hot water leakages, employees over confidence,
poor housekeeping, miss communication, slip/trip, entanglement, explosion/burst
etc
8.Safety Checks and precautions:
- Ø
Ensure all the
required competent man power is available and are using job related specific
PPEs.
- Ø
Ensure all the
resources are available.
- Ø
Ensure adequate
illumination at all the operating/working areas.
- Ø
Ensure proper
ventilation at all the operating/working areas
- Ø
Ensure no any
slippery area or accumulation of water at all the operating/working areas
- Ø
Ensure no
walkway/road blocks
- Ø
Ensure proper housekeeping
at all the operating/working areas
- Ø
Ensure firefighting
system/appliances is healthy and ready to use on immediate requirement
- Ø
Avoid use of mobile
while working
- Ø
Ensure all the
rotating parts of equipment are guarded fully
- Ø
Ensure all the hot
surfaces of the Boiler are insulated properly
- 9.Pre-start up checks-I
- Ø Ensure all
maintenance activities on Boilers are completed & work permits are closed
and equipment are normalised for operation.
- Ø Ensure all
equipments pre-start up trials conducted and are healthy to operate
continuously.
- Ø Ensure Boiler’s all
man hole doors (Furnace, super heater, bank zone, drum, economiser, plenum
hopper, furnace front hopper etc) are closed.
- Ø Ensure Boiler
thermal expansion pointers are available at all the desired locations and their
initial readings are okay.
- Ø Ensure ESP and APH
man hole doors are closed.
- Ø Ensure all safety
valves Gags are removed.
- Ø Ensure steam drum
vent, super heater vents and drains are open
- Ø Ensure start up
vent MOV is open and control valve is closed initially
- Ø Ensure water wall
headers all drains are closed
- Ø Ensure main steam
stop valve and bypass valves are closed
- Ø Ensure IBD &
CBD root valves are open and MOV valve is closed
- Ø Ensure DM water
pump is healthy and its valve to Deaerator is open for initial make up.
- Ø Ensure HP & LP
dosing pumps are healthy and their discharge valves to steam drum and Deaerator
are open.
- Ø Ensure Deaerator inlet
steam line valve is closed
- Ø Ensure deaerator
vent line valve and vacuum breaker valves are open
- Ø Ensure Deaerator
outlet to BFP inlet valve is open
- Ø Ensure all BFPs
suction valves are open and discharge valves are closed
- Ø Ensure all BFPs are
healthy to start on immediate requirement
- Ø Ensure feed control
stations (30% and 100%) isolation valves and MOVs are open and control valves
are in closed condition.
- Ø Ensure attemperator
isolation valves are open and control valve is in closed condition
- Ø Ensure Bagasse
screw feeders and extractors are heathy and their pre-trial is done
- Ø Ensure coal
spreaders bearing cooling water lines inlet & outlet valves are open
- Ø Ensure FD & SA
air dampers to furnace and OFA ducts are open and are set at desired positions.
- Ø Ensure instrumentation
& service air compressors are healthy and ready for immediate use.
- Ø Ensure maintenance
activities on AHP are completed and ready to take in service
- Ø Ensure ESP hopper
heaters and insulator heaters are ON
- Ø Ensure APH bypass
damper is open and main damper is partially or fully closed
- Ø Ensure Coal
handling plant and Bagasse handling plants are healthy and their interlocks
tests are conducted and found okay.
10.Pre-start
up checks-II
Tank level
- Ø Ensure Drum level
is 40-50%
- Ø Ensure Deaerator
level is 65%
- Ø Ensure Feed water
tank level is 70-80%
- Ø Ensure DM water
storage tank levels are 80-90%
- Ø Ensure cooling
tower level is 80%
- Ø Ensure tank levels
showing in are matching with local gauge glass levels.
- Ø Ensure feed water
parameters are normal
Fuel
- Ø Ensure abundant Bagasse/coal
is available at yard
- Ø Ensure Bagasse/coal
parameters (Moisture, Ash & GCV) are normal
- Ø Ensure bagasse
silos are full and silo gates are open
- Ø Ensure coal bunker
level is 80-90%
- Ø Ensure tractor
dozers and JCBs are available at yard
- Ø Ensure Diesel level
at DG tank is 90-95% and another 3000-4000 litres diesel is available for
immediate top up
- Ø Ensure Diesel
transfer pump is healthy and running normal
11.Boiler start up Procedure
- Ø Stack fire wood/ baled bagasse inside the furnace for light up
- Ø Start ACWP pump and ensure all the parameters like discharge water
pressure, bearing vibrations, temperature etc are normal
- Ø Start the Instrumentation air compressor and ensure all the operating
parameters are normal by evidencing loading and unloading pressures are as per
desired.
- Ø Start service air compressor and ensure all the operating parameters are
normal
- Ø Start the ESP rapping system
- Ø Start the ash handling system
- Ø Start the coal spreaders
- Ø Start the Sub merged belt conveyor (SMBC) and ensure enough water level in
conveyor trough.
- Ø
Fire the fire woods
and slowly rise the furnace temperature up to 175-200 deg C
- Ø
Start Bagsse handling
system and maintain silo levels 100%
- Ø
Start ID fan at 10%
reference followed by FD & SA fans and ensure balanced draft in furnace i.e
+ or – 2 to 3 mmwc and ensure fans operating parameters (Bearing vibration
& temperature) are normal.Note that, initially one stream of fans shall be
started and second stream shall be started once boiler reached at rated main
steam pressure and temperature.
- Ø
Ensure SA fans static
pressure at discharge is 400-450 mmwc initially and increase gradually based on
fuel feeding.
- Ø
Start CR fan and
maintain discharge static pressure 350-400 mmwc
- Ø
Start fuel feeding
system, start bagasse screw feeder followed by bagasse extractor at 5 to 10%
reference initially
- Ø
Gradually go on
increasing the furnace temperature by increasing fuel feeding slowly.
- Ø
Based on fuel
feeding, gradually rise ID, FD & SA fans speed and always ensure balanced
draft in furnace.
- Ø
Keep continuous communication
with Boiler field team and get the feedback on combustion in furnace.
- Ø
At drum pressure 2
kg/cm2 close drum air vent valves
- Ø
At steam pressure 3
to 5 kg/cm2, close all the super heater air vent valves.
- Ø
Start HP & LP
dosing system and ensure operating parameters (Discharge pressure, flow &
tank levels) are normal.
- Ø
Start rising the
Boiler pressure and temperature as per OEM given start up curve.
- Ø
Keep crack open CBD
valve
- Ø
If drum level is
coming down, start the BFP and maintain the drum level. Initially maintain the
drum level through single element (30%) control valve and keep it in manual
mode.
- Ø
If drum level increases,
give blow down through IBD. Note that, during start up drum level can be
maintained in the range of 30 to 80%. Do not allow to cross drum level > 85%
- Ø
At 5 to 7 Kg/cm2 main
steam pressure, close the primary super header drain valves.
- Ø
At pressure 7 to 10
kg/cm2, stop the firing & give blow down through IBD and water wall bottom
headers for 1 mi. Ensure normal drum level (40-50%) during blow downs.
- Ø
At 7 to 10 Kg/cm2
main steam pressure, close the secondary super header drain valves.
- Ø
At 10 to 15 Kg/cm2
main steam pressure, open start up vent control valve 10% and then close the
radiant super heater header drain valves.
- Ø
Gradually open the start-up
vent control valve as per requirement to ensure minimum cooling steam flow
through super heater coils and also to rise the main steam temperature
- Ø
Always ensure that,
minimum cooling steam is flowing through the super heaters when Boiler is under
firing.
- Ø
Keep on noting down
the Boiler all headers thermal expansion readings at various temperature and
pressure. And escalate if thermal expansions found non-uniform.
- Ø
Ensure Ash is
discharging from all the hoppers (Plenum, Economiser, APH and ESP hoppers)
- Ø
Ensure bearing
vibrations of BFP and fans are normal.
- Ø
Ensure fuel feeding
and handling system are running normal.
- Ø
At 40-45 kg/cm2,
gradually open the main steam by pass valve and start to charge the main steam
line.
- Ø
Check and confirm the
steam and water coming out from main steam drain lines.
- Ø
Gradually increase
the main steam pressure and temperature and open main steam stop valve slowly
(MSSV) after ensuring steam line has heated up and condensate has been removed
completely. Note that, before opening MSSV, pressure at inlet and outlet of the
valve is almost equal, this helps for easy operation of the valve
- Ø
After opening MSSV,
close by pass valve.
- Ø
After ensuring proper
charging of the main steam line, give clearance to Turbine engineer for vacuum
pull up and other start up activities. And open the MSSV as per their
requirement.
- Ø
Increase the main
steam pressure and temperature up to rated parameters i.e pressure 110 kg/cm2
and Temperature 545 deg C
- Ø
At rated pressure and
temperature, start the second stream of fans i.e ID, FD & SA fans &
ensure fan & motor’s bearing vibration and temperatures are normal.
- Ø
When boiler steam
flow reaches more than 30% of its MCR, close the start-up vent control valve.
- Ø
Charge ESP at inlet
flue gas > 120 deg C
- Ø
After normalisation
of start-up, once again ensure all equipment bearing vibration and temperatures
are normal and there not exist any abnormality.
- Ø
Take drum level
controller in Auto mode.