Codes & standards of practice for thermal power plant equipments

Sl No.

Particular

Code/standards of practice

A

Boilers

 

1

Code of practice for Constructions in steel

IS 800

2

Rules for construction of power boilers

ASME Section I

3

IBR materials

ASME BPVC SEC-II

4

Construction of heating boilers

ASME BPVC SEC-IV

5

Non-destructive testing

ASME BPVC SEC-V

6

Code of practice for design loads for buildings structures.

IS 875

7

Criteria for Earthquake Resistant – Design of Structures

IS 1893

8

Code for unfired pressure vessels

IS 2825

9

Indian Boiler Regulation

IBR 1950

10

Welding and Brazing Qualifications

ASME Section IX

11

Power piping

ASME B 31.1

12

Construction of pressure vessels

ASME BPVC SEC-VIII

13

Acceptance test for steam generator

DIN 1942

14

APH performance test code

ASME PTC 4.3

15

Boiler performance test

ASME PTC 4.1

16

Deaerator performance test code

ASMEPTC 12.3

17

Specification for wrought aluminium and aluminium alloys sheet and strip (For General Engineering Purpose)

IS 737       

18

Design & construction of RCC chimney

IS 4998-1992

B

REFRACTORY & INSULATION

 

1

Moderate heat duty fire clay refractories Group-A

IS:6           

2

High heat duty fire clay refractories

IS:8           

3

Insulating bricks

IS : 2042      

4

Method of determination of thermal conductivity of thermal insulation material

IS3346  

5

Code of practice for storage and handling of insulating materials

IS10556

6

Industrial application and finishing of thermal insulting materials at temperatures above 80 deg C and up to 700 Deg. C

 

IS14164

7

Specification for Bonded Mineral Wool

IS: 8183       

8

Hexagonal wire netting for general purpose

IS 2150        

9

Methods of test for mineral Wool Thermal Insulation Material

IS3144 

 

 

 

C

STEAM TURBINE & AUXILARIES

 

1

Duplex oil coolers design

ASME SEC-VIII, TEMA “C”

2

Steam ejector design

ASME SEC-VIII, DIV-1,TEMA “C”

3

Steam condenser design

HEI-IX EDITION

4

Thermal acceptance test for steam turbine

DIN 1943

5

Steam turbine performance test

ASME PTC 6

6

Surface condenser performance test codes

ASME PTC 12.2

7

Overall plant performance

ASMEPTC 46

D

WTP

 

1

Chemical dosing tanks design

BS 4994 1987

2

DM water storage  tank

IS 803

3

WTP vessels design

IS 2825

E

PUMPS ,COMPRESORS & FANS

 

1

Centrifugal pumps performance test code

ASME PTC 8.2

2

Design of Pumping Systems that use Centrifugal

Pumps

 

PIP RECP001

3

Design of ASME B73.1 and General Purpose pump

Base plates

 

PIP RESP002 

4

Seal Flush and Lubrication Guidelines for Centrifugal

Pumps

 

PIP REEP001

5

Compressors  performance test codes

ASMEPTC 10

6

Guide for selection installation and maintenance of air

Compressor up to 10 bars.

 

IS 6206        

7

Code of practice for testing of positive air displacement type

Compressors and exhausters

 

IS 5456        

8

Air receivers for compressed air installation

IS: 7938        

9

Fans  performance test codes

ASMEPTC 11

F

BELT CONVEYORS

 

1

Specification for troughed belt conveyors

IS: 1891  

2

Code of practice for conveyor safety

 

IS: 4776

3

Specification for pulleys for belt conveyors

IS: 7403  

4

Specification for idlers for belt conveyors

 

IS8598 

G

MAINTENANCE

 

1

Bars and Keyways for Flexible couplings

AGMA 9002

2

Pipe Threads, General Purpose

ASME B1.20.1

3

Cast Iron Pipe Flanges and Flanged Fittings

ASME B16.1

4

Pipe flanges and flanged fittings

ASME B 16.5

5

Roller Bearings –Dynamic Load Ratings and Rating Life – Part 1 : Calculation Methods.

 

ASME STD 9

6

Specification  for  Forgings,  Carbon  steel,  for  Piping

Components

 

ASTM  A105 

7

Specification for Seamless Carbon Steel Pipe for High

Temperature Service.

 

ASTM A106

H

ELECTRICAL & INSTRUMENTATION

 

1

Design of Power transformer

IS 2026

2

Code of practice for earthing.

IS: 3043 - 1987

 

    3

Guide for safety procedures and practices in electrical work: General.

IS: 5216(Part-1)-1982

 

 

4

General requirements for switchgear and control gear for voltages not exceeding 1000 V AC or 1200 V DC

IS:4237 - 1983

 

 

 

5

Air break switches, air break dis-connectors, air-break switch disconnectors and fuse-combination units for voltages not exceeding 1000 V AC or 1200 DC : General requirements

IS:4064(Part-1)-1978

 

6

Miniature air break circuit breakers for voltages not exceeding 1000 volt

IS: 8828 - 1978

 

    7

Residua current operated circuit breakers.

IS:12640 - 1988

8

Contactors for voltages not exceeding 1000 V AC or 1200 V DC.

IS:2959 - 1985

9

PVC Insulated cables for working voltages up to and including 1100 V.

IS:694 - 1990

 

Interview questions & answers on Boiler Alkali Boilout


 











1-Why do you carry out an Alkali boil out of a Boiler?

Alkali Boil out is done for

  • To remove oil & grease
  • To remove rust, scale  

2-When you will carry out alkali boil out on Boilers?

Alkali boil out is carried out for new boilers or Boiler where maintenance works like Bank tubes replacement, SH coils replacement are done.

3-List down the chemicals required for Alkali boil out of a Boiler

  • Hydrous Tri-Sodium Phosphate (Na3PO4.12 H2O)
  • Anhydrous Di-Sodium Phosphate (Na2HPO4)
  • Wetting agent (Surfactant / Detergent)

4-What is the ratio of selection of Disodium phosphate & detergents for alkali boil out

Quantity of Anhydrous Di-Sodium Phosphate (Na2HPO4) = Hydrous Tri-Sodium Phosphate X 20-25%

Quantity of Wetting agent (Surfactant / Detergent) = Hydrous Tri-Sodium Phosphate X 5-6%

 5-What are the two conditions for newly erected boilers for carrying out Alkali Boil out?

Boiler’s Hydraulic test should be completed

Boilers’ refractory dry out procedure should be completed

6-What are the pre-checks to be carried out before carrying out Alkali Boil out?

Pre-checks:

1-Ensure Boiler erection work is completed & its all auxiliaries trials taken & found okay

2-Ensure Fuel handling & fuel feeding system is okay & trial is being taken with respect to Mechanical, Electrical & instrumentation

3-Ensure Deaerator & related pumps are ready & can be taken into line readily

4-Ensure DM water is available

5-Ensure sufficient quantity of fuel is available at yard or at bunker

6-Ensure all equipment are hooked up to DCS

7-Ensure sufficient local PG & TG are avail be at Boilers

8-Ensure competent team is available

9-Ensure chemicals required for boil out & testing are available

10-Ensure all sample points are identified & competent person/team is there to collect the sample as per per decided frequency.

11-Ensure chemical dosing system is available

12-Ensure drain lines/flushing lines sample/sample lines are extended to safe location

7-Write down the procedure of Alkali Boil out in detail?

Procedure:

  1. Maintain the drum level just 6” -8”below the drum man hole door
  2. Initially, collect the required chemicals at drum platform as per dosage quantity decided
  3. Dissolve all the chemicals into water & then pour the chemical mixture into the drum from man hole
  4. After pouring, close the manhole door & raise the drum level up to normal operating level or just 2” below the normal operating level.
  5. Light up the boiler as per Boiler start-up & light up SOP
  6. Raise the Boiler pressure & temperature as per Boiler pressurizing curve
  7. Ensure thermal expansion of Boiler is happening & is uniform at all the headers
  8. Give IBD when drum pressure reaches 5 to 6 kg/cm2
  9. Raise the boiler pressure slowly & bring it to 50% of normal operating pressure or 40 kg/cm2, whichever is lower.
  10. Boil the chemical at same pressure for 10-12 hours.
  11. During boil out keep crack open CBD valve to avoid line & valve chocking
  12. During boil out period, operate the IBD for 15-20 second at every one hour & ensure water is replenished every time you give blow down.
  13. Note: Do not take drum level gauge glass into line during alkali boil out, keep one set of drum level transmitter on line
  14. At the end of the boiling period, collect the sample of IBD sample & test for oil traces. If the oil level is not in the allowable limit, then again add the chemicals & start boiling until the sample oil parameter meets the desired value.
  15. In order to decide the boil out is completed, the oil traces of 3 samples collected at 15 minute span should be < 5 ppm (Ensure consistency in results)
  16. After boil out, stop the boil out procedure & Box up the boiler & allow to cool the Boiler.
  17. During cooling period operate the blow down valves of drum & water wall panel bottom headers at least 2-3 times throughout the cooling period. And ensure normal water level in drum every time.
  18. Open the drum & super heater vents at pressure 2 kg/cm2
  19. Start rinsing the boiler, until the drain water pH equals to feed water pH
  20. After rinsing, drain the boiler completely & at the same time start to make up the boiler with DM water until the drain water pH becomes equal to feed water pH
  21. For flushing the super heater coils, raise the boiler pressure up to 40 kg/cm2 by Boiler feed pump (Hydraulic test of boiler at 40 kg/cm2 pressure) & then flush the water with from drain valve present before MSSV.This rinsing procedure is continued until the drain water pH becomes the makeup feed water
  22. Open the drum manhole doors & clean the internal surfaces with wire brushes
  23. Cut the stub ends/inspection caps of bottom headers & put wooden block in cut caps tightly.
  24. Again fill the boiler with feed water up to normal operating level & remove the wooden blocks one by one to remove the debris, scale or any other foreign materials from headers.
  25. Repeat above procedure for all bottom headers, then inspect all bottom headers for any debris, scale & foreign materials.
  26. After ensuring, everything is okay, then inspection caps should be welded subsequently radiography & hydraulic test should be done.

Boiler feed pumps start up & shutdown procedure






                    


                 Start-up Pre-check lists

  • Ensure Boiler feed pump is not in permit for maintenance works
  • Ensure all the maintenance activities on pumps are completed
  • Ensure equipment are normalized from electrical & mechanical side
  • Ensure Boiler feed pump is free from obstacles
  • Ensure enough lighting or illumination is available there
  • Ensure pump coupling is well guarded by robust coupling guard
  • Ensure Pumps local field instruments like pressure gauges, switches, vibration sensors, DP gauges are healthy
  • Ensure coupling is free to rotate

Starting procedure:

Start permissive (interlocks)

  • Ensure deaerator level is normal
  • Ensure feed pumps suction valves is open
  • Ensure cooling water line & outlet valves to bearings & mechanical seals are open and also water is circulating through the lines.
  • Ensure bearing temperatures are normal
  • Ensure bearing vibration showing DCS is zero
  • Ensure there is no alarm exists for strainer DP (differential pressure)
  • Ensure suction pressure is normal
  • Ensure discharge valve of the pump is closed
  • Ensure minimum recirculation valve or ARC valve is in open condition
  • Ensure balance leak off line valve to deaerator is open (In some valves are not provided to balance leak off line)

Start-up sequence

  • Take clearance from electrical & field person to start the pump
  • After getting the clearance from both the team, start the pump by giving minimum set point 80% if it is VFD driven.
  • Once the pump started, ensure pump will attain minimum 40% RPM in just 10 seconds (in case of journal bearing pumps).For non-journal bearing pumps speed ramp up time is not recommended specifically.
  • During speed ramp up check bearing vibrations & temperatures are normal.
  • Ensure pressure in the discharge pressure gauge is increasing slowly & has reached rated pressure at rated speed.
  • Then check the vibration, bearing temperatures & sound from pump.
  • Check & ensure the correctness of balance leak off line pressure
  • Wait for stabilization of the pump, once the pump attained rated parameters, check the motor current, temperature & vibrations & ensure they are within permissive limit.

Also recheck pump bearings vibration, temperatures & any abnormal sound from pump.

Pump normal shutdown procedure

  • For VFD driven pumps reduce the pump speed to 80% (for start delta driven pumps speed cannot be reduced)
  • Close the pump’s discharge valve
  • Then stop the pump

Do not’s for Boiler feed pumps

  • Do not rotate the pump in reverse direction, reverse direction leads the seize of pump
  • Don not run the pump if its suction water temperature is more than design/required
  • Do not operate the pump at less than 80<% load for long time to avoid damage to the bearings
  • Do not close the auto recirculation line valve
  • Do not close the balance leak off line valve (if provided)
  • Do not stop the pump with discharge valve open
  • Do not throttle the suction valve of the pump at lower load, can throttle discharge valve

 

 For related articles read

powerplant & calculations

 

 

 

 

 


15-Emergencies in power plant operation

Most visited posts