SOP: Standard Operating Procedures
SOP is to
provide a harmonized organizational framework for the operation of equipments and system.
Objectives of SOP
SOPs are
detail-oriented documents and provide step-by-step instructions as to how
employees within an organization must go about completing certain tasks and
processes.
SOP of Centrifugal Pumps:
START:
For
starting of a centrifugal pump proceed as stated below. However, when a
pump is put on remote & auto, its suction and discharge valves are normally
kept open unless specific logic and protection is implemented.
- Ensure there are no work permits on
equipment & equipment is in normalized condition.
- Ensure tank level is normal.
- Ensure suction valve is open &
suction pressure is normal.
- Ensure field all instruments are in
service.
- Ensure proper lubrication for pump
bearing
- Ensure cooling water flow & pressure
to bearings & mechanical seal (If provided)
- Ensure
Discharge valve is closed.
Note: For high discharge head pumps, normally discharge valve is in closed
condition and there will be minimum recirculation valve. And low discharge head
pumps discharge valve is in open condition
- Ensure that all the protection and
interlocks are in service.
- Prime the pump by opening air vent from
pump body or discharge vent.
- Give start- command by operating LPB or
from DCS.
- Once pump achieves normal speed, open
discharge valve slowly.
- Check current, vibration, bearing
temperature, any noise etc. and record.
SOP STOP:
- To stop a
centrifugal pump follow below mentioned steps.
- Keep integral by pass open & close
discharge valve, .
- Issue stop command either from local
push button or from DCS.
- Keeps cooling water flow some more time
to gland cooling etc.
- If the pump is kept as stand by, don’t
close CW line valve
- If the pump is stopped for maintenance,
isolate suction valve, discharge integral bypass, minimum re-circulation line
valve and balancing leak off line valve.
- Stop cooling water flow to pump gland.
SOP of positive
displacement pumps:
Plunger pump, reciprocating pump, screw
pump& gear pump are such pumps in this category. MOP, LDO pump are gear
pumps, lime dosing pump etc. are of screw pumps.
Pumps like HP/LP dosing pumps are
plunger pump which are normally used in power plant.
START:
- Follow the steps below for startup of
such pump.
- Ensure there are no work permits on
equipment & equipment is in normalized condition.
- Ensure normal tank level.
- All field instruments are in service.
- Ensure proper lubrication for pump
bearing.
- Ensure suction & discharge valves
are open.
Note: Positive displacement pumps should be always started with discharge
valve open
- Ensure that integral pump relief valve
& that of on discharge line are not gagged.
- Ensure that all the protection and
interlocks are in service.
- Prime the pump by opening air vent from
pump body or discharge vent.
- Give start- command by operating LPB or
from DCS.
- Check current, vibration, bearing
temperature, any noise etc.. and record the data.
SOP STOP:
Switch off keeping all the valves on.
Reference books for power plant O&M
Cooling Water Pump/Tower
To take cooling tower in service,
proceed as stated below.
- Ensure that Cooling Tower sump is filled
with makeup water up to operating level.
- Tower distribution header valves
are opened.
- CW return water line valves are open.
- CW pumps are available for operation and
free to rotate.
- CT fans are available for operation.
- CT fan gearboxes are filled with
requisite lube oil (LO) and up to operating level.
- Protections for CWP and CT fan are in
service.
- Ensure field instruments are in service.
- Open suction valve for selected pump,
keep discharge valve close.
- Prime pump by opening air release valve
on pump.
- Start CW pumps and gradually open the
discharge valve.
- Charge cooling water in condenser, lubricant
oil (LO) cooler, and generator cooler.
- Check discharge pressure, vibration, bearing
temperature and motor current.
- Check distribution of cooling water in
tower and adjust deck valve to make it uniform.
- Maintain sump level. Put other cooling
water pump on auto.
Note:
Before putting any pump on auto, ensure that
pump’s suction and discharge valves are open and priming of the pump is done.)
SOP Lube Oil cooler & Oil filter change over
SOP Boiler Feed Water Pump start up
Follow the steps given below
- Ensure there are no work permits on
equipment & equipment is in normalized condition.
- Ensure Deaerator level is normal
- Ensure pump suction pressure is normal
- Pump and Motor bearings are properly
lubricated and oil cups contain oil.
- Ensure suction strainer differential
pressure is normal
- All protection and interlock are in
service.
- All field instruments are in service.
- CW line for bearing cooling & gland
water cooling is open.
- Open suction valve, keep discharge valve
close.
- Ensure minimum re circulation and
balancing leak off line valves are open.
- Start pump by operating Local start Push
Button or from DCS.
- Ensure pump has reached 50% RPM in just
10 seconds to avoid bearing failure & rubbing of balance & counter
balance discs.
- Gradually open discharge valve. If
integral by pass valve is provided, open by pass valve first. Once Feed line is
pressurized, main discharge valve can be opened fully.
- Check all parameters, bearing
temperature, vibrations, suction / discharge pressure, balance leak off
pressure, motor winding temperature etc.
- Put other pump(s) on auto.
SOP Instrument Air Compressor
(Reciprocating)
Follow the steps given bellow to start a
compressor
- Ensure there are no work permits on
equipment & equipment is in normalized condition.
- All protection and interlock are in
service.
- All field instruments are in service.
- Sufficient lubricant oil (LO) is present
in crank sump.
- CW is charged in compressor and after
cooler and flow switch is reset.
- Moisture Traps are in service.
- Suction air filter is cleaned.
- Discharge valve is open.
- Start compressor.
- Check loading and unloading of compressor.
- Record loading unloading current and
pressure.
- Check discharge temperature.
Pump Change Over SOP:
- Ensure
that stand by pump is available for operation.
- Prime
the pump after opening its suction valve. (Where minimum re circulation line is
provided, open re circulation line valve).
- Start
pump either from local or from remote.
- Open
discharge valve and close minimum re circulation line valve.
- Gradually
close discharge valve of previous pump. (where minimum re circulation line is
provided , open re circulation line valve before closing discharge valve)
- Ensure
that incoming pump is maintaining all parameters like discharge pressure,
bearing temperature & vibrations.
- Switch
off the previous pump.
Boiler Gauge Glass Operation
Initial line up SOP
- Crack open the steam cock. Wait for some
time till the gauge glass is heated slowly.
- Crack open the water cock.
- Close
the drain cock & vent valve.
- Open the steam cock and water cock
fully.
SOP for Gauge glass flushing
- Close
the water cock and open the drain cock for some time.
- Close
the drain cock and open the water cock.
Note:
Water should return to its normal
working level quickly. If this does not happen, then there is a blockage in the
waterside
- Then
Close the steam cock and open the drain cock for some time.
- Close
the drain cock and open the steam cock.
Note:
If the water does not return to its
normal working level quickly, then there is blockage in the steam side.
Charging of Main Steam Line
This procedure
is applicable when main steam line is depressurized and first boiler is coming
into service. Proceed as follows for charging main steam line.
- Ensure that boiler has achieved at least
60% of its rated pressure
- (for detail operations of boiler
refer boiler operation from OEM manual).
- Ensure that that all the drain line
valves are open along with stream trap by pass.
- Open MSSV by pass partially so that line
steam pressure is at 5 kg/ cm2.
- Heat up line at least for 10 min.
- Increase pressure up to 10 kg/ cm2 for
another 10 min. To control main steam pressure line, warm-up vent can be opened
and regulated.
- Once dry steam is observed coming out from all the drains, close the
steam trap by pass and keep all the traps in service.
- Increase pressure of the steam line near
about the boiler pressure and open MSSV. Before operating MSSV, care to
taken that steam pressure before and after MSSV is more or less same. To match
the steam pressure warm up vent can be throttled.
- Increase pressure and temperature as
required for turbine start up.
- It is to be noted that increase of
temperature up to 300 deg C should be 3-5 deg C per minute. Above 300 degC the
increase of main steam line should be 5-7 degC per minute.
SOP Ejector System
Normally ejector system consists of one
set of Hogger and 2 main ejectors. For ACC ejector system there is
One set of Hogger system and 2 set of
service ejector. Each service ejector set consists of 2 nos of ejectors, 1 in
1st stage and 1no ejector in 2nd stage.
To take Hogger ejector in service
follow following guidelines
- Ensure auxiliary steam is available at
desired pressure and temperature
- Ensure vacuum breaker valve fitted on
steam condenser is closed
- Ensure cooling water is circulating in
the condenser and the turbine gland is charged fully at 0.1 kg/cm2
- Note: During cold start up gland sealing
is charged after taking hogger into line (after vacuum pulling) i.e say at
vacuum -0.2 to -0.5 kg/cm2 & During hot start up gland sealing is charged
before taking hogger into line (before vacuum pulling).
- Ensure live steam line to ejector steam
lines drain are kept open.
- Charge the main steam line to ejector
steam & temperature control valve.
- Ensure the rated pressure (10 kg/cm2 or
as specified by OEM) and temperature.
- Once the rated parameters are reached
open the steam valve of starting or hogger ejector.
- Observe the steam is vented to the
atmosphere.
- Then open the ejector airline valve.
- Observe vacuum inside the condenser
increasing slowly and will reach 60 to 70% of rated vacuum within 20 minutes
Read More SOPs.
Emergency operation guide in power plants
Slop fired Boiler SOP
Turbine oil flushing SOP
Coal handling plant SOP
Boiler refractory dry out SOP
Boiler feed pump start/stop SOP
Steam turbine cold, warm & hot start up SOPS
Boiler Alkali Boil out SOPs
Boiler Hydraulic test SOP